Re: Process Chain stuck in Yellow - framework error upon completion (e.g. follow-on job missing)

Hi Janardhan,

 

Thanks for your input. Whenever we faced the above issue, we found that there are overlapping of same loads of different timings which lead to that issue.

 

However as you said, I have reached out to the Basis guys to understand the current SPS we are on.

We are on: NW 7.0 EHP1 on SPS level 10. And they have confirmed that there is no SPS 32 yet.

 

So, are you talking about NW 6.4 or NW 7.0? Please let me know, so that we will even try to upgrade it.

 