Re: ESS CATS Timesheet without Project Systems

$
0
0

depends on the budget ure customer has.

lets talk differetn scenarios:

1. customer has loads of budget: then--> implement PS and then do the cats thingy.

2. we have budget constraints--> then the logical steps would be to:

a. figure out the exact mapping betwen the prject filed in the customer .net system against which times are booked.

b. create a z-field in cats for that.

c. get employees to book time in cats and use that z-field as well ..

d. the saved times usually stay in catsdb... so now u have hours against projects data in it u get it out and send the file across tot he .net based system where they do the upload...

 

cheers