Re: Scheduling semi finished in CRP

$
0
0

Dear,

 

Check the setting of OPU3 for Adjust scheduling.

Adjust dates in lead time scheduling :- 1 Adjust dates to Operation start.

 

It is possible if the routing of product A having two operations one for B and one for C You will get the result as you want.

In routing for Product A  assign component C to first operation and B to second operation and  maintained wait time at the operation level (1 Day).  Do the lead time scheduling and check the results.

 

Hope clear to you.

 

Regards,

R.Brahmankar