- Should I reconcile remaining challan quantity with 542 material document ?
- If I reconcile challan with 542 material document , in report J1IFR challan quantity is reconciled but 542 material document is not updating , it should be update same as 101 material document.
3. Do I need to develop J1ifr report or we have any alternative please suggest
1) Yes, quantity reconcialltion can be done for 542 Movement type.
2) Have you assigned the Movement type 542 in the Subcontracting CIN settings?